Update on new risers: I've attached a few photos on the new risers. One shows the new 316 SS schedule 40 pipe risers temporarily installed on the JetHot coated exhaust flanges. The problem here is that it's impossible to screw the risers tightly into the flanges and have them aligned properly to joint the exhaust hoses. I sent the risers to DeAngelo Marine Exhaust in Ft Lauderdale where they cut they installed a Marmon flange on each riser and fabricated insulation blankets. This permitted us to screw the threaded nipple of the riser tightly into the exhaust flange, then alight the riser to the hoses before tightening the V-clamp on the Marmon flange.
The other photos show the risers installed. The threaded nipple is not insulated in these photos. We will install the insulation blankets on these after we splash, run up the engines and make sure there are no leaks at the Marmon flanges.
The weight of the Sch 40 SS pipe required installation of the threaded struts you see in the photos to keep excessive stress of of the Marmon flanges.
You can see various items in these photos that would be inappropriate, embarrassing, or unsafe if the boat was in service. These things will be dealt with before we splash.